Perusahaan Listrik Negara
PT Perusahaan Listrik Negara is an Indonesian government-owned corporation which has a monopoly on electricity distribution in Indonesia and generates the majority of the country's electrical power, producing 176.4 TWh in 2015. It was included in the Fortune Global 500 lists of 2014 and 2015.
History
The history of the electricity sector in Indonesia began at the end of 19th century when Dutch colonialists installed the first electrical generators. The largest of the electricity distribution companies was the Nederlands Indische Gasmaatschappij which was originally a gas utility company. In World War II, the Japanese took control of the electricity sector. After Indonesian Independence on 17 August 1945, revolutionary Indonesian youth took control of the electricity sector in September 1945 and handed facilities over to the Republican government. The history of the electricity sector since then has been one of continuing institutional changes.On 27 October 1945 President Sukarno established the Jawatan Listrik dan Gas with a generation capacity of only 157.5 MW. On 1 January 1961, the bureau of Electricity and Gas was changed into BPU PLN which dealt in the areas of electricity, agas, and coke. On 1 January 1965, BPU-PLN was replaced with two state owned enterprises, Perusahaan Listrik Negara handling the electricity sector and Perusahaan Gas Negara handling gas. The capacity of the electrical-power generators of PLN, then, was 300 MW. There were further institutional changes during the 1970s, 1980s, and 1990s.
In September 2002 the Electric Power Act, was promulgated. The act formally deregulated the electricity sector. The new act required an end to PLN's monopoly on electricity distribution within five years after which time private companies were to be permitted to sell electricity directly to consumers. All companies were to use PLN's existing transmission network. However, the act was annulled in 2004 by the Constitutional Court. As a result, the electricity sector was in an uncertain legal situation for some years. A new electricity act, Act No 30 of 2009, was introduced to provide greater legal certainty although this act, too, was controversial because, as was the case with the earlier 2002 act, it legislated to end PLN's monopoly in the sector.
Operations
In the first half of 2011, the PLN generated 88 terawatt-hours. The firm generated around 24% of its output using oil-based fuel with plans to reduce the share to 3% by 2013 and 1.7% by 2014. The forecast for the full year is around 182 tWh.Capacity and organisation
At the end of 2015, the PLN's total generating capacity was estimated at around 34,262 MW. Throughout 2016, PLN planned to boost its installed generation capacity by 1,932 MW.Maximum capacity | Peak load | |
Java-Bali | 21,257 | 16,150 |
Western Indonesia | 4,602 | 4,299 |
Eastern Indonesia | 2,603 | 2,484 |
Total | 28,462 | 22,933 |
Main indicators have been increasing along with overall economic growth in Indonesia although the growth of revenue per unit sold has been slow:
Employees | Capacity | Production | Sold | Output value | Average revenue | Average revenue | |
Units | Number | MW | TWh | TWh | Rp trill | Rp/kWh | US cents/kWh |
2005 | 43,762 | 22,515 | 124.5 | 105.9 | 64.0 | 604 | 6.2 |
2006 | 43,048 | 24,846 | 131.7 | 112.6 | 74.9 | 665 | 7.4 |
2007 | 42,537 | 25,224 | 139.7 | 121.2 | 77.4 | 639 | 6.8 |
2008 | 42,715 | 25,594 | 148.0 | 129.0 | 86.4 | 670 | 6.1 |
2009 | 42,096 | 25,637 | 156.8 | 134.6 | 90.9 | 676 | 7.2 |
2010 | 43,638 | 26,895 | 176.0 | 149.0 | 103.0 | 700 | 8.0 |
2011 | 44,343 | 29,268 | 184.2 | 158.7 | 112.8 | 714 | 7.8 |
2012 | 50,287 | 32,901 | 200.3 | 174.0 | 126.7 | 728 | 7.5 |
2013 | 49,833 | 34,206 | 216.2 | 187.5 | 153.5 | 818 | 6.1 |
2014 | 46,068 | 37,226 | 228.6 | 198.6 | 186.6 | 940 | 7.5 |
2015 | 47,594 | 38,265 | 234.0 | 202.8 | 209.8 | 1,034 | 7.5 |
2016 | 51,158 | 39,785 | 248.6 | 216.0 | 214.1 | 991 | 7.3 |
2017 | 54,820 | 39,652 | 254.7 | 223.1 | 246.6 | 1,105 | 8.1 |
Source: Indonesian Statistics Bureau, Statistik Indonesia, Jakarta, and Statistik PLN, Jakarta.
PLN only. Does not include generation capacity in the main independent power producers which had an approximate capacity of another 5,600 MW at the end of 2012.
Includes wholesale electricity purchases by PLN from independent power producers and resold to consumers.
Average revenue shown = Output value divided by sales.
Estimate in US cents = Average Rp revenue adjusted by the end-year exchange rate.
Growth | Capacity utilization | Capacity utilization | Labor productivity | Losses | |
Units | % per year | kWh/MW | % | GWh/employee | % |
2005 | 4.5 | 5,530 | 63 | 2,845 | 15 |
2006 | 2.3 | 5,126 | 58 | 2,959 | 12 |
2007 | 11.8 | 5,647 | 64 | 3,349 | 15 |
2008 | 5.6 | 5,877 | 67 | 3,522 | 14 |
2009 | 4.2 | 6,116 | 70 | 3,725 | 14 |
2010 | 12.2 | 5,351 | 61 | 4,033 | 15 |
2011 | 4.7 | 5,218 | 59 | 4,153 | 14 |
2012 | 9.5 | 4,509 | 51 | 4,011 | 14 |
2013 | 7.9 | 6,321 | 72 | 4,338 | 13 |
2014 | 5.7 | 6,141 | 70 | 4,962 | 13 |
2015 | 2.4 | 6,115 | 70 | 4,289 | 13 |
2016 | 6.2 | 6,249 | 71 | 4,859 | 13 |
2017 | 2.5 | 6,423 | 73 | 4,646 | 12 |
Source: Calculated from previous table.
Growth = annual production growth. Capacity utilisation = kWh generated per kW of generation capacity ; calculations assume that there is 4,200 MW of generating capacity in the independent power producers which sell electricity to the PLN. Labor productivity = Total GWh generated per employee in the PLN. Losses = sales as a % of production.
The Indonesian Government, and the senior management of the PLN, are officially committed to ongoing reforms designed to improve the efficiency of operations of the electricity supply sector in Indonesia. Performance indicators show some significant improvements in certain key measures in recent years. However, the overall reform process is often slow, hampered by the fact that the environment within which the state-owned PLN operates is closely regulated and often politicised.
Management
The PLN is Indonesia's second-largest state company by assets. The top level management, headed by the president director, reports to a government-appointed board. The board and the PLN management in turn report to the Minister of State-Owned Companies. President directors of PLN since 1979 have been as follows:Start | End | Name |
1979 | 1984 | Suryono |
1984 | 1988 | Sardjono |
1988 | 1992 | Ermamsyah Jamin |
1992 | 1995 | Zuhal |
1995 | 1998 | Djiteng Marsudi |
1998 | 2000 | Adi Satria |
2000 | 2001 | Kuntoro Mangkusubroto |
2001 | 2008 | Eddie Widiono |
2008 | 2009 | Fahmi Mochtar |
2009 | 2011 | Dahlan Iskan |
2011 | 2014 | Nur Pamudji |
2014 | 2019 | Sofyan Basir |
2019 | 2019 | Sripeni Inten Cahyani |
2019 | incumbent | Zulkifli Zaini |
- Difficulties came to light during early 2011 over arrangements during the management period of the long-serving PLN president director Eddie Widiono Suwondho. Questions arose over certain procurement procedures which he supported. He was taken into questioning by Indonesia's Corruption Eradication Commission in March 2011. In December 2011 he was convicted to five years imprisonment for charges that centred on the appointment of a company to handle the provision of outsourced services for the PLN.
- In mid 2019, Sofyan Basir was suspended as president director following the decision of the Corruption Eradication Commission to indict him on a charge of corruption for his alleged role in graft relating to the construction of a power plant in the province of Riau.
- Sripeni Inten Cahyani was Acting CEO for the latter part of 2019 until Zulkifli Zaini was appointed president director in late 2019.
Policies
- Use, for the first time, of liquefied natural gas as a fuel for some of PLN's generation plants
- Near-finalisation of the first 10,000 MW fast-track generation program announced some years earlier
- Registration of 5 million pre-paid customers into the PLN distribution system.
Service
Finances
The PLN has—and has had, for many years—considerable trouble with internal revenue flows. For one thing, government-regulated tariffs are often too low to cover operational costs and have not been set at a level sufficient to make a reasonable contribution towards capital costs for many years. For another thing, there is widespread consumer resistance to payment of electricity bills. The cash flows of the company are often weighed down with overdue debts from consumers.- As just one example, in the Banyumas district of Central Java in late 2011, it was reported that 60 percent of the PLN's 140,000 customers in the area were overdue with payments for their electricity bills causing the company over $300,000 in losses each month. Of the customers in arrears, 13,000 were considered very bad customers and were targeted for disconnection. But the PLN's efforts to improve debt collection, both in Banyumas and in many other areas of Indonesia, often meet with considerable consumer resistance. In Banyumas, consumers complained that the PLN's efforts to improve debt collection were unfair and failed to reflect the social obligations expected of state-owned enterprises.
- Not long afterwards, the PLN was involved in an incident in the Central Java city of Surakarta where the municipality had overdue bills owing of close to $1 million to the PLN. Following PLN company policy to pursue a more aggressive approach to collect overdue bills, the PLN imposed a blackout on street lamps in Surakarta just before Christmas 2011. The city municipality quickly arranged payment but arranged the settlement along with a protest and suggested that the PLN should consider the interest of the public before taking this type of action. To reinforce the point, the mayor of Surakarta, Joko Widodo, made a highly publicised personal visit to the local PLN office to deliver the Rp 8.9 billion in cash in the form of hundreds of bundles of notes and coin.
Apart from internal revenue flows, the PLN relies on large government subsidies to support operations and, especially, capital expenditure. The average tariff for electricity at the end of 2011 was estimated to be around Rp 729 per kWh while PLN's average cost of production was put at around Rp 1,100. The electricity subsidy provided from the national budget in 2011 was initially budgeted at Rp 65.6 trillion but the amount increased to Rp 91 trillion by the end of 2011. In March 2012 the government proposed a reduction in the electricity subsidies to the national parliament but the proposal was rejected. As a result, the PLN came under pressure to try to find economies to reduce the ballooning level of subsidies. Ignoring the subsidies, in 2016 PLN experienced a loss of Rp 31.63 trillion.
In recent years, as economic conditions in Indonesia have improved following the Asian financial crisis of 1997-98, PLN has also been able to undertake significantly increased borrowings through bond issues. In November 2011, for example, PLN issued $1 billion of debt at reasonable market prices. Demand for the debt significantly exceeded the supply of bonds on offer. In October 2012 it was reported that the PLN planned to issue 30-year USD bonds which had been graded BB by Standard and Poor's rating agency. Through the issuance of debt of this kind the PLN is both raising funds and participating in the development of the domestic debt market in Indonesia.
The PLN also accesses other government-supported sources of financing. In December 2011 the company received a Rp 7.5 trillion soft loan from the Indonesian state investment agency PIP. The soft loan was provided for a total period of 15 years with a 5-year grace period for capital payments at a relatively low interest rate of 5.25% per annum
Investment programs
The overall investment program in the public electricity sector in Indonesia is largely dependent on two fast-track 10,000 MW investment programs initiated in recent years. The programs are behind schedule.First 10,000 MW fast track program (FTP-1)
The first 10,000 MW fast track program commenced in 2006 and was originally scheduled to be completed by 2010. As of mid-2012, except for one plant all the power plants were behind schedule. The program was still incomplete towards the end of 2014.- Mid-2012: The government announced that as of mid-2012, slightly over 40% of the expected supply had been delivered. Problems causing delays included equipment availability, land-acquisition problems, and funding.
- End 2012: The PLN reported that around 48% of the total planned capacity of 9,877 MW had been realised. The remaining capacity of 5,127 MW was expected to come on line before the end of 2014.
- Late 2014: It was reported that FTP-1 would be completed in 2015.
Main plants in the program include the following:
Region | Province | Location | Capacity |
Java | - | - | - |
Bantan | Teluk Naga | 900 | |
Banten | Labuan | 600 | |
Banten | Suralaya | 625 | |
West Java | Indramayu | 990 | |
West Java | Pelabuhan Ratu | 1,050 | |
Central Java | Rembang | 630 | |
East Java | Pacitan | 660 | |
East Java | Paiton | 660 | |
Outer Islands | - | - | - |
Lampung | Tarahan Baru | 200 | |
North Sumatra | Medan | 400 | |
Aceh | Nagan Raya | 220 |
Second 10,000 MW fast track program (FTP-2)
A second 10,000 MW program was announced in 2010 but implementation is lagging following delays in FTP-1. The initial deadline for the second track was end-2016.- End 2012: The PLN announced that around 4,650 MW of the planned second stage would be on stream by end-2016. The ambitious original plan was that 49% of the second 10,000 MW fast track program would be made up of low-carbon geothermal plants. However, as of end-2012, 36 of the planned 52 geothermal plants were facing delays because of difficulty in obtaining access to sites in conservation areas or because of technical difficulties while a further 14 plants had not yet been put to tender.
- Late 2014: It was reported that the total size of the program had been expanded to 17,918 MW. However, progress under FTP-2 was reported to be slow. The initial deadline for completion had been extended by five years to 2020.
PLN Investment financing
expenditures. Financing flows for the capital expenditures were forecast as follows:
Source | Cost | Cost | Share | Forecast use of funds |
PLN internal budget | 33.6 | 3.7 | 48 | Construction of power plants; evaluation of 10,000 MW fast-track program; distribution |
National budget | 8.9 | 1.0 | 13 | Distribution systems in rural areas; renewable energy |
Subsidiary loans | 9.8 | 1.1 | 14 | National power grids |
Bank loans | 16.7 | 1.9 | 24 | Other capital items |
Total | 69.0 | 7.6 | 100 |
PLN Investment projects and plans
The PLN has plans to build a significant number of coal mine-mouth power plants in Sumatra and Kalimantan. These include the following:- Plans for power plants in Sumatra with a combined capacity of 7,300 MW by 2020. One of the aims of this program is the goal of optimising coal usage to, amongst other things, accelerate development in the producing regions of Indonesia. In early 2012 the PLN announced that contracts had been awarded for the construction of three coal-fed plants with a total combined capacity of 2,140 MW in Sumatra: South Sumatra 5 ; South Sumatra 6 ; and South Sumatra 8. It is also expected that in June 2012, the PLN will begin the tender process for three mine-mouth plants in Sumatra: South Sumatra 9 ; South Sumatra 10 ; Jambi. The three plants are expected to come on stream in 2016.
- A mine-mouth coal-fired plant in Asam, South Kalimantan, with a capacity of 530 MW is expected to come on-line by the end of 2012. This is the Indonesia's third existing mine-mouth coal-fired plants; other plants are the Ombilin plant and Bukit Asam plant, both in West Sumatra.
Long-term plans (2013-2022)
Sumatra-Java Grid
To provide power from plants in Sumatra to the main Indonesian electricity market in Java, in April 2012 PLN began the tender process for a Rp 20 trillion project expected to be completed in 2017 which would provide 3,000 MW of power. The plan is for AC current to be converted to DC current in the Muara Enim Converter Station, South Sumatra and be converted back into AC current in the Bogor Converter Station, West Java. Between these sites, a 40 km 500 kv submarines cable would connect Ketapang in Lampung and Salira in Banten.Geothermal power
Although in principle Indonesia is well-supplied with sources of geothermal energy, exploiting geothermal energy in Indonesia has proceeded slowly in recent years. In mid-2012, PLN officials noted that 13 geothermal plants across Indonesia were 'stuck in exploration stages' and likely to miss development deadlines. A range of practical problems often caused problems—in some cases, initial drilling had failed to find wells with satisfactory yields of energy; in other cases, problems with local infrastructure and obtaining permits from local officials and forestry agencies had caused delays.Hydro power
There is considerable hydro power potential in Indonesia. However, most potential capacity is at sites which are hard to access and quite distant from any sizeable markets. There is believed to be hydro power potential of over 22,000 MW in Papua and perhaps another 16,000 MW in South Kalimantan and Central Kalimantan. Total Indonesian hydro power potential has been put at over 75,000 MW, with only 5,705 MW being utilised. 96 locations across the country with a total capacity of 12,800 MW would be developed 60 percent by PLN, while the rest would be offered to independent power producers.One problem, especially in the Outer Islands off Java, is that relatively small hydro plants often experience operational problems such as shortages of water flow. In Lampung in September 2012 for example, towards the end of the dry season, two small hydropower stations operated by PLN ceased operation, causing blackouts in the region. Localised problems of this sort are common across much of the Outer Islands.