Perusahaan Listrik Negara


PT Perusahaan Listrik Negara is an Indonesian government-owned corporation which has a monopoly on electricity distribution in Indonesia and generates the majority of the country's electrical power, producing 176.4 TWh in 2015. It was included in the Fortune Global 500 lists of 2014 and 2015.

History

The history of the electricity sector in Indonesia began at the end of 19th century when Dutch colonialists installed the first electrical generators. The largest of the electricity distribution companies was the Nederlands Indische Gasmaatschappij which was originally a gas utility company. In World War II, the Japanese took control of the electricity sector. After Indonesian Independence on 17 August 1945, revolutionary Indonesian youth took control of the electricity sector in September 1945 and handed facilities over to the Republican government. The history of the electricity sector since then has been one of continuing institutional changes.
On 27 October 1945 President Sukarno established the Jawatan Listrik dan Gas with a generation capacity of only 157.5 MW. On 1 January 1961, the bureau of Electricity and Gas was changed into BPU PLN which dealt in the areas of electricity, agas, and coke. On 1 January 1965, BPU-PLN was replaced with two state owned enterprises, Perusahaan Listrik Negara handling the electricity sector and Perusahaan Gas Negara handling gas. The capacity of the electrical-power generators of PLN, then, was 300 MW. There were further institutional changes during the 1970s, 1980s, and 1990s.
In September 2002 the Electric Power Act, was promulgated. The act formally deregulated the electricity sector. The new act required an end to PLN's monopoly on electricity distribution within five years after which time private companies were to be permitted to sell electricity directly to consumers. All companies were to use PLN's existing transmission network. However, the act was annulled in 2004 by the Constitutional Court. As a result, the electricity sector was in an uncertain legal situation for some years. A new electricity act, Act No 30 of 2009, was introduced to provide greater legal certainty although this act, too, was controversial because, as was the case with the earlier 2002 act, it legislated to end PLN's monopoly in the sector.

Operations

In the first half of 2011, the PLN generated 88 terawatt-hours. The firm generated around 24% of its output using oil-based fuel with plans to reduce the share to 3% by 2013 and 1.7% by 2014. The forecast for the full year is around 182 tWh.

Capacity and organisation

At the end of 2015, the PLN's total generating capacity was estimated at around 34,262 MW. Throughout 2016, PLN planned to boost its installed generation capacity by 1,932 MW.
Maximum capacityPeak load
Java-Bali21,25716,150
Western Indonesia4,6024,299
Eastern Indonesia2,6032,484
Total28,46222,933

Main indicators have been increasing along with overall economic growth in Indonesia although the growth of revenue per unit sold has been slow:
EmployeesCapacity Production SoldOutput valueAverage revenue Average revenue
UnitsNumberMWTWhTWhRp trillRp/kWhUS cents/kWh
200543,76222,515124.5105.964.06046.2
200643,04824,846131.7112.674.96657.4
200742,53725,224139.7121.277.46396.8
200842,71525,594148.0129.086.46706.1
200942,09625,637156.8134.690.96767.2
201043,63826,895176.0149.0103.07008.0
201144,34329,268184.2158.7112.87147.8
201250,28732,901200.3174.0126.77287.5
201349,83334,206216.2187.5153.58186.1
201446,06837,226228.6198.6186.69407.5
201547,59438,265234.0202.8209.81,0347.5
201651,15839,785248.6216.0214.19917.3
201754,82039,652254.7223.1246.61,1058.1

Source: Indonesian Statistics Bureau, Statistik Indonesia, Jakarta, and Statistik PLN, Jakarta.
PLN only. Does not include generation capacity in the main independent power producers which had an approximate capacity of another 5,600 MW at the end of 2012.
Includes wholesale electricity purchases by PLN from independent power producers and resold to consumers.
Average revenue shown = Output value divided by sales.
Estimate in US cents = Average Rp revenue adjusted by the end-year exchange rate.
Growth Capacity utilization Capacity utilization Labor productivityLosses
Units% per yearkWh/MW%GWh/employee%
20054.55,530632,84515
20062.35,126582,95912
200711.85,647643,34915
20085.65,877673,52214
20094.26,116703,72514
201012.25,351614,03315
20114.75,218594,15314
20129.54,509514,01114
20137.96,321724,33813
20145.76,141704,96213
20152.46,115704,28913
20166.26,249714,85913
20172.56,423734,64612

Source: Calculated from previous table.
Growth = annual production growth. Capacity utilisation = kWh generated per kW of generation capacity ; calculations assume that there is 4,200 MW of generating capacity in the independent power producers which sell electricity to the PLN. Labor productivity = Total GWh generated per employee in the PLN. Losses = sales as a % of production.
The Indonesian Government, and the senior management of the PLN, are officially committed to ongoing reforms designed to improve the efficiency of operations of the electricity supply sector in Indonesia. Performance indicators show some significant improvements in certain key measures in recent years. However, the overall reform process is often slow, hampered by the fact that the environment within which the state-owned PLN operates is closely regulated and often politicised.

Management

The PLN is Indonesia's second-largest state company by assets. The top level management, headed by the president director, reports to a government-appointed board. The board and the PLN management in turn report to the Minister of State-Owned Companies. President directors of PLN since 1979 have been as follows:
StartEndName
19791984Suryono
19841988Sardjono
19881992Ermamsyah Jamin
19921995Zuhal
19951998Djiteng Marsudi
19982000Adi Satria
20002001Kuntoro Mangkusubroto
20012008Eddie Widiono
20082009Fahmi Mochtar
20092011Dahlan Iskan
20112014Nur Pamudji
20142019Sofyan Basir
20192019Sripeni Inten Cahyani
2019incumbentZulkifli Zaini

In late 2011, the new president director of the PLN, Nur Pamudji listed three milestones for PLN as targets for 2012:
The reliability and quality of electricity supply has steadily improved in Indonesia in recent decades. Supply is more reliable in Java because the grid is relatively well-developed compared to the situation in the Outer Islands where most areas are serviced by localised systems often powered by small diesel plants. However power outages are still common, even in Java. There was, for example, a particularly severe power outage in 2005 which reportedly affected around 100 million people across Java and Bali for over five hours.

Finances

The PLN has—and has had, for many years—considerable trouble with internal revenue flows. For one thing, government-regulated tariffs are often too low to cover operational costs and have not been set at a level sufficient to make a reasonable contribution towards capital costs for many years. For another thing, there is widespread consumer resistance to payment of electricity bills. The cash flows of the company are often weighed down with overdue debts from consumers.
Theft of electricity is common in many parts of Indonesia as well. In recent years, the PLN has been moving to tighten up on problems of non-payment of bills as well as theft. Prepaid meters are now required for all new housing units.
Apart from internal revenue flows, the PLN relies on large government subsidies to support operations and, especially, capital expenditure. The average tariff for electricity at the end of 2011 was estimated to be around Rp 729 per kWh while PLN's average cost of production was put at around Rp 1,100. The electricity subsidy provided from the national budget in 2011 was initially budgeted at Rp 65.6 trillion but the amount increased to Rp 91 trillion by the end of 2011. In March 2012 the government proposed a reduction in the electricity subsidies to the national parliament but the proposal was rejected. As a result, the PLN came under pressure to try to find economies to reduce the ballooning level of subsidies. Ignoring the subsidies, in 2016 PLN experienced a loss of Rp 31.63 trillion.
In recent years, as economic conditions in Indonesia have improved following the Asian financial crisis of 1997-98, PLN has also been able to undertake significantly increased borrowings through bond issues. In November 2011, for example, PLN issued $1 billion of debt at reasonable market prices. Demand for the debt significantly exceeded the supply of bonds on offer. In October 2012 it was reported that the PLN planned to issue 30-year USD bonds which had been graded BB by Standard and Poor's rating agency. Through the issuance of debt of this kind the PLN is both raising funds and participating in the development of the domestic debt market in Indonesia.
The PLN also accesses other government-supported sources of financing. In December 2011 the company received a Rp 7.5 trillion soft loan from the Indonesian state investment agency PIP. The soft loan was provided for a total period of 15 years with a 5-year grace period for capital payments at a relatively low interest rate of 5.25% per annum

Investment programs

The overall investment program in the public electricity sector in Indonesia is largely dependent on two fast-track 10,000 MW investment programs initiated in recent years. The programs are behind schedule.

First 10,000 MW fast track program (FTP-1)

The first 10,000 MW fast track program commenced in 2006 and was originally scheduled to be completed by 2010. As of mid-2012, except for one plant all the power plants were behind schedule. The program was still incomplete towards the end of 2014.
The FTP-1 comprises 35 power plants, mostly coal-fired. Ten of the plants are in Java-Bali. The other 35 mainly-smaller plants are in the Outer Islands.
Main plants in the program include the following:
RegionProvinceLocationCapacity
Java---
BantanTeluk Naga900
BantenLabuan600
BantenSuralaya625
West JavaIndramayu990
West JavaPelabuhan Ratu1,050
Central JavaRembang630
East JavaPacitan660
East JavaPaiton660
Outer Islands---
LampungTarahan Baru200
North SumatraMedan400
AcehNagan Raya220

Second 10,000 MW fast track program (FTP-2)

A second 10,000 MW program was announced in 2010 but implementation is lagging following delays in FTP-1. The initial deadline for the second track was end-2016.
At the end of 2011 it was announced that expected expenditures for PLN during 2012 would be around Rp 260 trillion made up of Rp 191 trillion for operational costs and Rp 69 billion for capital
expenditures. Financing flows for the capital expenditures were forecast as follows:
SourceCost Cost Share Forecast use of funds
PLN internal budget33.63.748Construction of power plants; evaluation of 10,000 MW fast-track program; distribution
National budget8.91.013Distribution systems in rural areas; renewable energy
Subsidiary loans9.81.114National power grids
Bank loans16.71.924Other capital items
Total69.07.6100

PLN Investment projects and plans

The PLN has plans to build a significant number of coal mine-mouth power plants in Sumatra and Kalimantan. These include the following:
The PLN has issued an Electricity Supply Business Plan for the period 2013-2022. The plan talks of an additional generating capacity generating need of 59.5 GW over the period. Total estimated expenditure is put at around $125 billion. Useful details are set out in the .

Sumatra-Java Grid

To provide power from plants in Sumatra to the main Indonesian electricity market in Java, in April 2012 PLN began the tender process for a Rp 20 trillion project expected to be completed in 2017 which would provide 3,000 MW of power. The plan is for AC current to be converted to DC current in the Muara Enim Converter Station, South Sumatra and be converted back into AC current in the Bogor Converter Station, West Java. Between these sites, a 40 km 500 kv submarines cable would connect Ketapang in Lampung and Salira in Banten.

Geothermal power

Although in principle Indonesia is well-supplied with sources of geothermal energy, exploiting geothermal energy in Indonesia has proceeded slowly in recent years. In mid-2012, PLN officials noted that 13 geothermal plants across Indonesia were 'stuck in exploration stages' and likely to miss development deadlines. A range of practical problems often caused problems—in some cases, initial drilling had failed to find wells with satisfactory yields of energy; in other cases, problems with local infrastructure and obtaining permits from local officials and forestry agencies had caused delays.

Hydro power

There is considerable hydro power potential in Indonesia. However, most potential capacity is at sites which are hard to access and quite distant from any sizeable markets. There is believed to be hydro power potential of over 22,000 MW in Papua and perhaps another 16,000 MW in South Kalimantan and Central Kalimantan. Total Indonesian hydro power potential has been put at over 75,000 MW, with only 5,705 MW being utilised. 96 locations across the country with a total capacity of 12,800 MW would be developed 60 percent by PLN, while the rest would be offered to independent power producers.
One problem, especially in the Outer Islands off Java, is that relatively small hydro plants often experience operational problems such as shortages of water flow. In Lampung in September 2012 for example, towards the end of the dry season, two small hydropower stations operated by PLN ceased operation, causing blackouts in the region. Localised problems of this sort are common across much of the Outer Islands.