Philippine National Railways
The Philippine National Railways is a state-owned railway company in the Philippines, operating a single line of track on Luzon. As of 2016, it operates one commuter rail service in Metro Manila and local services between Sipocot, Naga City and Legazpi City in the Bicol Region. PNR began operations on November 24, 1892 as the Ferrocarril de Manila-Dagupan, during the Spanish colonial period, and later becoming the Manila Railroad Company during the American colonial period. It became the Philippine National Railways on June 20, 1964 by virtue of Republic Act No. 4156. The PNR is an agency of the Department of Transportation.
PNR used to operate over of route from La Union to the Bicol Region. However, neglect reduced PNR's service. Persistent problems with informal settlers in the 1990s contributed further to PNR's decline. In 2006, Typhoons Milenyo and Reming caused severe damage to the network, resulting in the suspension of the Manila-Bicol services. In 2007 the Philippine government initiated a rehabilitation project aiming to remove informal settlers from the PNR right of way, revitalize commuter services in Metro Manila, and restore the Manila-Bicol route as well as lost services in Northern Luzon. In July 2009, PNR unveiled a new corporate identity and inaugurated new rolling stock. Long-distance Bicol services resumed in June 2011, but were suspended again in October 2012, leaving only local service between Naga and Sipocot. Local service between Naga and Legazpi resumed in October 2015.
History
Spanish period
On June 25, 1875, under a royal decree issued by King Alfonso XII of Spain, the required Inspector of Public Works of the Philippine Islands was requested to submit a railway system plan for Luzon. The plan, which was submitted five months later by Don Eduardo Lopez Navarro, was entitled Memoria Sobre el Plan General de Ferrocarriles en la Isla de Luzón, and was promptly approved. A concession for the construction of a railway line from Manila to Dagupan was granted to Don Edmundo Sykes of the Ferrocarril de Manila–Dagupan, later to become the Manila Railway Company, Ltd. of London, on June 1, 1887.The Ferrocarril de Manila–Dagupan, which constitutes much of the North Main Line today, began construction on July 31, 1887 with the laying of the cornerstone for Tutuban station, and the line opened on November 24, 1892. Expansion of the Philippine railway network would not begin until the American colonial period, when on December 8, 1902, the Philippine Commission passed legislation authorizing the construction of another railway line, which would later form the South Main Line.
American period
Additional legislation was passed in 1909 authorizing further railway construction and the use of government bonds to finance them, and by 1916, of track had been built by the company, which had reorganized itself as the Manila Railroad Company of New Jersey. Apart from the North and South Main Lines, other lines branching out of these two main lines were built, like the lines to Rosales and San Quintin, Pangasinan; San Jose and Cabanatuan, Nueva Ecija; Dau, Carmen, Floridablanca and Arayat, all in Pampanga province, as well as inside the US Air Base Fort Stotsenburg which became Clark Air Base; Antipolo, Taytay, and Montalban, a spur line to Nielsen Field in what is now Ayala Avenue in the Makati Financial District from Culi Culi Station, all in Rizal province; Cavite City and the nearby US Air Base of Sangley Point as well as Noveleta and Naic, both in Cavite province; Canlubang, Santa Cruz and Pagsanjan all in Laguna province; Batangas City and Bauan both in Batangas province, as well as a line connecting San Pablo City in Laguna to Luta in Batangas province ; Port Ragay in the Bicol province of Camarines Sur; as well as till Tabaco from Legaspi, Albay.Similar to other railroads at the time, the Manila Railroad Company suffered from financial difficulties during World War I, and on February 4, 1916, the Philippine Assembly passed Act No. 2574, authorizing the Governor-General to negotiate for the nationalization of the MRR's assets. The MRR was eventually nationalized in January 1917, with the Philippine government paying ₱8 million to the company's owners and assuming ₱53.9 million in outstanding debt. Consequently, the MRR's management shifted from British to American hands, and in 1923, José Paez became the first Filipino general manager.
During the 1920s, the MRR embarked on a general program of improvements as a result of operating surpluses accrued over much of the decade. The ₱30 million program allowed for the extension of railway service on the North Main Line from Dagupan to San Fernando in La Union, the extension of the South Main Line to Legazpi in Albay, and the construction of several spur lines. The last rail connecting Manila to Bicol was laid on November 17, 1937 and regular direct service between Manila and Legazpi was inaugurated on May 8, 1938, and by 1941, the MRR operated of track.
On December 14, 1941, at the start of World War II, the MRR was put under U.S. military control, and on December 30, the MRR management was ordered to allow U.S. military forces to destroy network infrastructure, resulting in very extensive damage to train facilities and right of way. Coupled with further damage during the Japanese occupation of the Philippines, where the Imperial Japanese Army operated services on a very limited basis using whatever could be salvaged, and further fighting in the Allied liberation of the Philippines by the combined American and Filipino forces a few years later, damages to railroad property amounted to around ₱30 million. By the end of the war, only were operational, largely as a result of the United States Army and the Philippine Commonwealth Army performing temporary repairs on railroad infrastructure for military purposes. MRR property was later returned to the Philippine government on February 1, 1946.
Post-war period
Following the war, the MRR was able to restore limited services, using surplus military equipment and payments made by the United States Army and the Philippine Commonwealth Army for use of railway facilities in the Philippines Campaign. By July 1, 1947, funded by a ₱20 million rehabilitation allocation set aside by the Philippine government, around 75% of the entire railway network prior to 1941 was rehabilitated. By 1951, with the MRR receiving ₱3 million in war reparations funds, of track, representing 82.5% of the total railway network prior to 1941, was in operation. Later in the 1950s, the MRR fleet of locomotives was converted from steam to diesel engines, and the company was given a new charter under Republic Act No. 4156, becoming the modern-day Philippine National Railways.Creation of PNR
Natural calamities such as the 1973 and 1975 floods disrupted services and forced the closure of several parts of the main lines. On July 23, 1979, President Ferdinand Marcos issued Executive Order No. 546, which designated the Philippine National Railways as an attached agency of the then Department of Transportation and Communications.In 1988, during the administration of Corazon Aquino, the North main line was closed, with trains unable to reach various provinces in the country. The South main line was also closed due to typhoons and floods, and the eruption of Mayon Volcano in 1993, in which ash flows and lava destroyed the rail line and its facilities. However, jeeps, buses and taxis were popular, and many people were swayed from the present service until 2009.
When Fidel V. Ramos succeeded Corazon Aquino, he decided to rehabilitate the South Main Line from Tutuban to Legaspi, and appointed Jose B. Dado as the new PNR general manager. A railway system running from Manila to Clark was also set to be constructed in the 1990s, when Ramos signed a memorandum of agreement with Juan Carlos I of Spain for its construction in September 1994, but the project was later cancelled due to disagreement on the source of funding.
Contemporary history
Rehabilitation attempts and the NorthRail project
The administration of Gloria Macapagal-Arroyo actively pursued the rehabilitation of the Philippine National Railways through various investments and projects designed to revive Philippine rail transport, despite the numerous problems involved. Total reconstruction of rail bridges and tracks, including replacement of the current 35-kilogram track with newer 50-kilogram tracks and the refurbishing of stations, were part of the rehabilitation and expansion process. The first phase, converting all the lines of the Manila metropolitan area, were completed in 2009. On July 14, 2009, Gloria Macapagal-Arroyo presided over the launch of the new diesel multiple units from Hyundai Rotem for the Philippine National Railways. As part of its new image, a new brand name, PNR Filtrack was added and a new PNR logo was unveiled until the succeeding administration decided to revert to the original logo.The San Cristobal bridge in Calamba, Laguna was rebuilt in May 2011. The Bicol Express train service was inaugurated on June 29, with a maiden voyage between Manila and Naga City plus a return trip back to the terminus on July 1. This inaugural trip was marred by the collapse of the embankment at Malaguico, Sipocot. It was discovered before the train passed through and was repaired. The restored Bicol Express intercity service was offered on a daily basis, running mostly during night time.
The Northrail project involved the upgrading of the existing single track to an elevated dual-track system, converting the rail gauge from narrow gauge to standard gauge, and linking Manila to Malolos City in Bulacan and further on to Angeles City, Clark Special Economic Zone, the Clark International Airport. The railway project was contracted out by the Arroyo administration in 2003 to China National Machinery and Equipment Corporation for an original cost of $421 million. This project was estimated to cost around US$500 million, with China offering to provide some US$400 million in concessionary financing. Construction of the railway was halted, then temporarily continued in January 2009, and then stopped again in March 2011, due to a series of anomalies with the foreign contractor, before finally being scrapped in 2011 by the Aquino administration on lingering legal issues and corruption allegations.
The DOTC has examined reviving the project by commissioning a feasibility study by CPCS Transcom Ltd. of Canada. Part of the study examined having a Malolos-Tutuban-Calamba-Los Baños Commuter Line.
Current developments
The current administration under Rodrigo Duterte is working towards the rehabilitation of the PNR, the establishment of a railway from New Clark City to Metro Manila, the North-South Commuter Railway, the reconstruction of the current South Commuter line, and the reestablishment of long-haul services to the south. Rehabilitation of tracks and stations has commenced.After nearly 20 years, PNR reopened the Metro North Commuter line, and launched the Caloocan-Dela Rosa shuttle line, on August 1, 2018. This would be followed by a steady expansion and reintroduction of rail services to the north, currently reaching to Malabon City, which has not seen rail activity for nearly 20 years. A plan to reactivate the Carmona line was bared as well, and the revival of cargo rail from Port Area, Manila to Laguna is now being planned.
On December 16, 2018, all commuter services saw changes in train runs and establishments of new termini, particularly in the recently revived Metro North Commuter. More train runs were added for the north currently terminating at Governor Pascual.
On November 16, 2018, PNR became a provisional member of International Union of Railways.
On May 21, 2019, DMCI won the contract for the construction of PNR North 1.
On June 14, 2019, PNR became ISO-certified for railway repair, rehabilitation, restoration and maintenance, train control and rolling stock maintenance, station operation and other related services. The certification was announced October 2, 2019.
Operations and services
The PNR currently operates in Metro Manila and the neighboring Laguna province. At the last years of regular intercity service along the system's entire length in the late 1980s, it served from Tutuban to San Fernando, La Union on the North Main Line and Legazpi, Albay on the South Main Line. Various branch lines also led to Batangas, Cavite, Nueva Ecija, Rizal and Tarlac. One of the branch lines that led to Carmona was intended to be reopened by 2019. This was not realized as of March 2020.Summary of services
Metro Commuter Line
''Metro North Commuter''
The reactivated Metro North Commuter ran initially from Caloocan to Makati and uses a single special fare matrix of PHP 12.00 for ordinary, and PHP 15.00 for air-conditioned. This was later extended to reach FTI in Taguig, now with a distance-based fare matrix. A Caloocan-Tutuban shuttle service also exists, using the original right-of-way once used for the Dagupan line. Originally terminating at 10th Avenue station while the historical Caloocan station was still being prepared for activation, the station now terminates at its originally intended station since September 10.DOTr and PNR are also working on reviving and reactivating rail services in areas prepared for NorthRail, such as Malabon and possibly Valenzuela. First proposed and planned last September 2018, the extension to Gov. Pascual Avenue and the re-establishment of the Governor Pascual Station in Malabon has been done, with new rail ties and narrow gauge rail tracks being restored. It reopened to the public on December 3, 2018.
Another extension, this time targeting Valenzuela City has been bared on August 14, 2019, and will require rebuilding a railroad bridge crossing Tullahan river that has been previously destroyed.
The line is provisional and services will be potentially interrupted when the elevated tracks are to be constructed, likely after the construction of NLEX Segment 10.1. The reconstructed lines are targeted for freight use as well as part of the system's extension to the north.
''Metro South Commuter''
The Metro Commuter, which was formerly called Commuter Express , serves as the commuter rail service for the Manila metropolitan area, extending as far south as Calamba City and Los Baños, both in Laguna. The PNR uses GE locomotives such as 900 Class, 2500 Class, and 5000 Class hauling Commex passenger cars as well as newly procured 18 Hyundai Rotem DMUs and KiHa 52 for this service. 203 series EMUs are now also used for Metro Commuter runs. MSC service using the new DMUs, KiHa 52, KiHa 350 and 203 series EMUs is currently offered between Tutuban and Alabang in Muntinlupa City. Currently, MSC makes 42 return services, 21 in each direction.Shuttle Service
The Shuttle Service is a commuter rail service initially introduced on January 27, 2014. This service used Hyundai Rotem DMUs and JR KiHa 52. There were 2 routes of the Shuttle Service, where trains stop at all stations along the routes: Tutuban – Sucat and Santa Mesa – Sucat. This train service ended May 23, 2014 to conduct maintenance on the rolling stocks and due to the consecutive three weeks of delays and cancellations of this train service.Formerly, plans for a third route plying Alabang – Calamba was to be introduced sometime in 2017. This service would use the reliveried two-car KiHa 350; This did not push through in 2018. However, with the commissioning of the new DOST Hybrid Train in 2019, this route is now under test run, currently free of charge, but with limited schedules.
In 2018, a new shuttle line was introduced with the 10th Avenue – Dela Rosa route beginning August 1, as part of the renovation of the line and the return of train services to Caloocan City. The revived train service had its first extension towards Sangandaan, the original Caloocan station since September 10, extending through FTI. The latest so far is the northwards extension to Governor Pascual in Malabon City since December 3, 2018.
A new shuttle line leading to the once-abandoned Carmona branch line is planned for reopening in 2019, and will originate from the Dela Rosa station in Makati City.
Bicol Commuter
The Bicol Commuter service is a commuter rail service in the Bicol Region, between stations in Tagkawayan, Quezon, and Legazpi, Albay, with Naga City in Camarines Sur acting as a central terminal. The service was launched on September 16, 2009, in time for the feast of Our Lady of Peñafrancia in Naga City. The trains made seven trips a day, alternating between Tagkawayan, Sipocot, Naga City and Legazpi. All services used KiHa 52 in revised blue livery.After further reductions, only the service between Naga and Sipocot was operating as of December 2013. Service resumed between Naga and Legazpi in October 2015 with one train a day.
Definitive plans to restore the entire route from Sipocot, Naga and Legazpi were bared with an inspection trip from Tutuban on September 20 with a rerailment crew, including certain areas of Quezon Province, in preparation of the restoration of more routes previously suspended.
Defunct services
Intercity services
PNR's intercity operations on its two main lines in Luzon have been indefinitely suspended since 2014.The South Main Line then served as the primary intercity service after the permanent closure of the northern line in 1991. However, PNR also ended its regular intercity services in 2006 due to natural disasters and poor track conditions, although the Bicol Express ran irregularly between 2009 and 2014. In Camarines Sur, liquefaction of the track's embankment caused a section of the line in Sipocot to sink. This allowed the inaugural service of the new Bicol Express in 2011 to slow down to a near-stop while passing through the area.
There are plans to revitalize both lines. The North Main Line is currently reserved for building the fully-elevated portion of the North–South Commuter Railway to Capas, Tarlac. The South Main Line is [|planned to be rebuilt and extended] to Matnog, Sorsogon. The spur line to Batangas City will also be rebuilt. Test runs along the South Main Line were conducted in September 2019. On September 21, 2019, a KiHa 59 and a rerailment train consisting of a newly-repainted PNR 900 class locomotive and a CMC coach conducted a test run from Tutuban to Naga.
North Main Line services
The North Main Line was first opened when the Manila–Dagupan Railway was opened in 1892. At its height between the 1950s and 1960s, the line once boasted full double-track railways from Tutuban to Dagupan and also served until San Fernando, La Union. It also had branch lines to various areas in Central Luzon. However, its services severely deteriorated in the 1980s. All regular operations outside Metro Manila ended in 1988. However, there was irregular service to Meycauayan railway station until all stations in Central Luzon were closed by the 1991 eruption of Mount Pinatubo.''Amianan Express''
The Amianan Express was a night train service that opened in 1974. It left Manila by 11 PM and arrived in San Fernando by 4:30 AM the next day. It was serviced by then-new PNR 900 class diesel-electric locomotives and five coaches capable of seating 912 people. After ending in San Fernando station, commuters would take the bus to Ilocos Norte and Sur, and Benguet. Later, it was expanded into two services, the Amianan Day Express and the Amianan Night Express. The Amianan Night Express ran faster than its day counterpart, the Amianan Day Express, making the run to San Fernando, La Union in five hours.Baguio train-road service
The difficulty of terrain to build new train lines prevented both MRR and PNR to have direct train services to Baguio City. Instead, they had two luxury train services then will be accompanied by either bus or car to Baguio, and an ordinary train-bus service. During the Commonwealth era, then-MRR operated a train-bus service to Baguio. Passengers would ride the train to either Dagupan or San Fabian in Pangasinan then take the bus to Baguio City. The first service was terminated during World War II. A second service was inaugurated by the MRR by around 1955. First-class passengers would ride the train from Tutuban to Damortis station in Santo Tomas, La Union, then will ride a limousine service of Chevrolet Bel Airs to Pines Hotel in Baguio City. It costed ₱45 for this package. Another service was opened during the PNR era with a bus service leading to Baguio City, with buses provided by Hino Motors. This service operated until all provincial services on the North Main Line were suspended by 1988.''Dagupan Express''
The Dagupan Express opened on February 10, 1979. It was serviced by CMC-300 class diesel multiple units. Like the Amianan Express, the Dagupan Express also ended in the 1980s after all North Main Line services terminated in Tarlac.''Ilocos Express''
The Ilocos Express was inaugurated on March 15, 1930. The services includes a dining car with catering provided by the Manila Hotel. Another variant of the service was the Baguio-Ilocos Express. Following the modernization program of the Manila Railway Company in 1955, the Ilocos Express featured a 7A class "De Luxe" coach until 1979, when the lack of operable air-conditioned coaches caused a switch to a "Tourist"-class coach. The company also operated the Paniqui Express in the 1930s, but that was eclipsed by the Ilocos Express. There were two accidents involving the service, one in 1939 and another in 1959.''Ilocos Special''
The fastest train operated by the PNR on the North Main Line was the Ilocos Special. The service started in 1973. This diesel multiple-unit train took four hours to run the 195 kilometer portion between Manila and Dagupan City.South Main Line services
Intercity services on the South Main Line ran between Manila and Legazpi between 1916 and 2014, including the intermittent Bicol Express and Mayon/Isarog Limited services between 2009 and 2014. The services also briefly extended to Sorsogon in the 1960s due to the trains' popularity as a form of transportation with the masses.''Bicol Express''
Bicol Express started operations between Manila and Aloneros station in Guinayangan, Quezon by 1919 along with the Lucena Express. A separate train between Pamplona and Tabaco, and between Port Ragay and Legazpi was opened by 1933. The Tabaco branch line during this era was closed in 1937 and instead, they linked these three sections into a single line. This formed the backbone of the South Main Line and was subsequently opened in 1938. This service was short lived and ended during the Japanese occupation of the Philippines in 1942. During this era, the Japanese government focused on rebuilding the North Main Line instead and extended it to Sudipen on the border between Ilocos Sur and La Union, and the south line's rehabilitation was cut to San Pablo, Laguna.After the line's post-war rehabilitation, another service was opened. The service immediately became popular with the public and more services were introduced on August 16, 1954. There are two services of this type: the daytime Bicol Express and the Night Express which was the night train counterpart. The Bicol Express leaving Manila was numbered 511 and its night counterpart leaving Legazpi was numbered 513. The Bicol Express leaving Legazpi was numbered 512 and the Night Express leaving Manila was numbered 514. The trains only stopped at six stations between Tutuban and Legazpi: Paco, Lucena, Tagkawayan, Sipocot, Naga and Ligao. Journey times lasted 13 hours between the two termini. Services were expanded until the 1970s.
By 1998, Bicol Express was the only intercity service on the South Main Line. More stations were also added into the line. It was renumbered as Train T-611 for the southbound and Train T-612 for the northbound. Another Bicol Express train was serviced by the second version of the General Manager's train, a trainset based on modified CMC-300 series DMUs already operating in PNR service. This was numbered T-577.
Since then, the service was discontinued by 2006 after natural disasters did serious damage to the tracks and bridges. Efforts to revive the service were unsuccessful. Since 2014, operations to the Bicol Region have been suspended. This is primarily because of typhoon damage to bridges. The PNR hoped to reopen the Bicol Express Service by about September 2014. Due to the damages brought by the Typhoon Rammasun, PNR announced that the Bicol Express' resumption of services would be further delayed until October and November 2014. Since then resumption of service has been repeatedly announced and then cancelled, most recently in late 2016. This was mostly because of the remoteness of the areas and the necessity of more extensive railway repairs, which has rendered the railways towards Tutuban and back impassable until very recently.
It has been decided in 2019 that the Bicol Express on its present infrastructure will be discontinued permanently and a new service to Bicol will be announced after [|the new standard gauge line] has been completed by 2021. This line will be built with Chinese funding and the trains will be served by diesel multiple units from CRRC Zhuzhou Locomotive.
''Lucena Express''
The Lucena Express was first opened in 1916 with a service between Malvar, Batangas and Aloneros in Guinayangan, Quezon. Later, the service was opened between Manila and Lucena. This train stopped at Blumentritt, Santa Mesa, Paco, San Pedro, Biñan, Santa Rosa, Calamba, Los Baños, College, Masaya, San Pablo, Tiaong, Taguan, Candelaria, Lutucan and Sariaya stations. It was discontinued in 1942 during the Japanese occupation and was later integrated with the Bicol Express after the war.''Mayon Limited''
In March 2012, another train service, the resurrected Mayon Limited, ran between Tutuban and Ligao. The train ran as Mayon DeLuxe on Monday, Wednesday and Friday from Tutuban as train T-713 with three air-conditioned carriages with reclining seats. The train returned on Tuesday, Thursday and Sunday as train T-714 from Ligao. On Tuesdays, Thursdays and Sundays the train ran as Ordinary train with non-reclining seats and cooling by fan. The departure as train T-816 was every Monday, Wednesday and Friday. The train did not run on Saturdays. The trains meet at Gumaca. As of September 2013, all operations to the Bicol Region, including the Mayon Limited, have been suspended.The original Mayon Limited service decades ago was hauled alternatively by French Alstom locomotives Series 1500, and General Electric locomotives, especially the U12C Series 1000, UM12C Series 2000, and U14/15C Series 900 and ran northward from Legazpi up the steep gradient leading to Camalig in the foothills of the Mayon Volcano with another locomotive pushing from the rear. The service was assigned as and was considered then as the fastest and the most modern train of the Philippine National Railways operating on the South Main Line.
''Manila Limited''
The Manila Limited was a train service between Manila and Iriga. One train leaves from these two termini each. Train 517 left Manila by 3 pm and arrive in Iriga by 4:15 am. Train 518 will leave Iriga by 2:50 pm and arrive in Manila by 2:35 am. It ended in 2006 when all regular intercity services were terminated.''Prestige Express''
The Prestige Express, also nicknamed the VIP Train from some rail enthusiasts of the time, was a limited express service from 1974 to 1981. It ran the full length of the South Main Line, but only stopped at only five stations in-between. In Manila, it only stopped at the historic Paco station. Afterwards, it stops at Lucena in Quezon, Naga in Camarines Sur, and in Daraga and Ligao in Albay. Like all services on the South Main Line, there were added. It service was replaced by the shorter Peñafrancia Express in 1981 that ended at Naga.It used two classes of Japanese-built diesel multiple units namely, the cowl unit-type multiple unit and the streamlined "General Manager's Train" or "Nikkō" train set. The latter train sets were named after the service of the same name and its body design was inspired by the 157 series while the nose's design was inspired by the 0 Series Shinkansen EMUs. Both DMUs were acquired in 1974 with the opening of the service. PNR later refurbished the IC-888 trainset in order to serve the Bicol Express in 1998 until 2004. This train was still stored in the Caloocan rail yard without any plans for scrapping as late as 2011.
''Peñafrancia Express''
The PNR inaugurated the Peñafrancia Express between Manila and Naga City in 1981. It became PNR's premium intercity service and also had airline-style features such as pre-recorded background music, snacks, caterers, and stewardesses. Unlike the preceding Prestige Express, it did not have specialized rolling stock. It was primarily a choice between the acquired refurbished Nikko train acquired from the previous Prestige service, and later the 900 class locomotive and hauled ICF baggage cars and sleeper coaches built in Madras, India.Initially they were non-stop between Paco Station in Manila and Naga City, save for when the Peñafrancia Express trains headed in opposite directions had to cross each other along the route in Quezon province. Later on, additional stops were added, mostly in the Bicol province of Camarines Sur with the train stopping in towns like Ragay, Sipocot, and Libmanan. This service ended by the late 1990s.
Non-passenger services
The PNR used to offer freight services, using General Electric U15C 900-series locomotives bought by the company in 1974. It is currently planned for a revival leading to the Manila North Harbor.There was also a limited mobile hospital service. The PNR also operated the PNR Motor Services, a bus service that led to towns that were not serviced by trains. The bus service ended by 1988.
Stations
The Philippine National Railways operates two different rail lines, namely the North Main Line and the South Main Line. Formerly, there were three spur lines, which served various parts of Luzon with its 138 active stations.Station layout
All PNR stations were and are presently at-grade, with most stations using a side platform layout. Most have only basic amenities, platforms and ticket booths. Rehabilitated stations along the Metro Manila line have been fitted with ramps for passengers using wheelchairs. Several stations have extended platforms, having an upper platform catering to DMU services, and a lower platform for regular locomotive-hauled services.As of August 2017, most of the stations are being extended and equipped with platform-length roofing, better ticketing office, and restrooms.
Future railway systems under the PNR, such as that of the new North–South Commuter Railway line, proposes elevated stations and platforms similar to the Manila LRT and MRT lines in select sections.
Modernization and expansion plans
The PNR system has suffered from decades of neglect and therefore, several plans to restore and expand the network has been proposed by various administrations. The Republic of Korea, the People's Republic of China, Japan and Indonesia have contributed to these plans. Most of these concern the revitalization and modernization projects of the mainlines in Luzon. As of 2019, the Duterte administration plans a complete overhaul of the PNR system, which involves electrification and conversion from narrow gauge to standard gauge, as well as from single to double track.Urban rail systems
North–South Commuter Railway
The North–South Commuter Railway, or the Clark-Calamba Railway, is the latest project to revitalize both the historic North and South Main Lines. First proposed as "NorthRail", a rapid transit system to connect Metro Manila to Clark International Airport that was to be co-funded by Spain, it had been subject to various cancellations related to funding. It finally came into shape in November 2017 after a resolution of a five-year dispute between the government and a Chinese contractor. The system now includes an expansion of the line to Laguna.The NSCR will be a 36 station, elevated railway system from New Clark City in Capas, Tarlac to Calamba, Laguna. It will be the first electrified main line in the country. Construction on the Tutuban-Malolos segment or PNR North 1 commenced on February 15, 2019. Once fully completed by 2025, it will accommodate at least 300,000 passengers between Northern Metro Manila and Bulacan alone. While the elevated line will be served by electrified trains, the existing lines below will be used for freight trains and/or existing commuter trains.
Rapid transit involvement
As part of the infrastructure program by president Rodrigo Duterte, East-West Rail was proposed by the East-West Rail Transit Corp., a consortium between Megawide, A. Brown Company Inc., and Private Equity Investment and Development Corp. It involves the financing, design, construction, and maintenance of a mostly-elevated rapid transit line from Diliman in Quezon City to Quiapo in Manila. In 2018, the PNR has said that it will help in building and operating the line. The line will have 11 stations on of mostly elevated track. The project is currently awaiting approval from NEDA to proceed. It is also currently tackling right-of-way issues, such as that of the España Boulevard alignment.Intercity projects
South Main Line reconstruction
On October 23, 2019, the Department of Transportation has announced that PNR and the Chinese government has agreed to restore and modernize the South Main Line between Calamba and Legazpi, Albay and eventually to Matnog, Sorsogon. Its gauge will also be widened from narrow gauge to standard gauge with new diesel multiple units from Chinese manufacturer CRRC Zhuzhou Locomotive. The line will initially operate as single-track before eventually upgrading to double track in the long run.For the meantime, PNR is currently testing a new Manila-Naga service using the newly-refurbished KiHa 59 trainset before the new South Main Line commences operations in 2021.
Calamba–Batangas City railway restoration
The Calamba–Batangas City branch of the South Main Line will also be restored. The National Economic and Development Authority approved the projects in September 2017 but no clear timeline of construction has been set. In a similar fashion to the South Main Line between Manila and the Bicol Region, it will be initially be opened as a single-track standard gauge line. It will be upgraded to double-track and electrification as part of the planned NSCR South Phase 2 proposed in 2014.Mindanao Railway
President Rodrigo Duterte expressed his support for the establishment of a railway system in the entire island of Mindanao which could be in operation after his term ends. The railway system to be built in Mindanao will have about 2,000 kilometers of track, and considered one of Rodrigo Duterte's primary infrastructure projects. The first phase, which is, would start construction in the third quarter of 2018 and was expected to be completed by 2022.High-speed rail
It was initially rumored before the announcement of the North–South Commuter Railway that a "high-speed train line" will connect Metro Manila and Clark International Airport. However, when the new line was announced, the actual maximum speed is only between for the commuter trains and for airport express trains and therefore does not qualify for true high-speed rail. Another speculation in form of a map for possible high-speed rail services around the country was spread throughout social media. Department of Transportation Undersecretary Timothy Batan falsified the claims but said that there are plans to build an HSR line and the current rail infrastructure being built are linked for future HSR development.Freight revival
In 2016, PNR has been interested in reviving its freight services with a planned signing of a memorandum of agreement between the railway and rail freight operator MRAIL for the rehabilitation of the rail lines to North Harbor and to restart the freight services starting 2017, which will also help reduce traffic congestion and truck use in the NCR. If completed, MRail will jointly operate the freight service with the PNR, which will end a long absence of railway freight services in the country. This will be the second time the PNR will partner with ICTSI.A statement made by MRail Inc., a subsidiary of Metro Pacific Investments Corp., said that discussions regarding PNR freight service revival from Port of Manila to the Laguna Gateway Inland Container Terminal resulted in the appointment of a new board at the Philippine National Railways. Representatives of PNR and ICTSI conducted an inspection of the ROW where the former railtracks leading to the North Harbor existed, signalling the start of the action to realize the cargo rail revival.
As of 2019, the freight revival plans are not in effect.
Rolling stock
PNR has operated several types of locomotives, carriages and multiple units as part of its fleet. As of 2019, the rolling stock used are primarily powered by diesel. The DOST Hybrid Electric Train may also function as a battery electric multiple unit although it is started by a diesel engine. All present rolling stock are in. PNR also has rail mounted cranes as supporting equipment with varying capacities from 0.5 to 30 metric tons.In late 2019, all trains in service except the 203 series-derived coaches underwent refurbishment and livery changes. The multiple units were given an orange and white color scheme and its windows were changed from having steel grills to polycarbonate windows that can resist stoning from illegal settlers while the locomotives have been painted orange.
Locomotives
During the first years of its operation as the Manila-Dagupan Railway, it operated tank engines mostly built in Scotland. The first tender engines appeared in 1907, when the company purchased eight 4-6-0 D class locomotives from the Scottish-English builder Kerr, Stuart and Company. After the Insular Government took over the company by 1917, the company became the Manila Railroad Company and a number of its previous tank engines were converted to tender locomotives as well. By 1919, the American manufacturer H.K. Porter built 20 more D class locomotives. The Porter locomotives will eventually replace the old Scottish locomotives by 1927. Afterwards, larger steam locomotives were purchased in 1929 and then by 1944. The last steam locomotive in service with the American-owned Manila Railroad Company was the Japanese-built 300 class, based on the JNR Class D51. All steam locomotives were considered obsolete by 1956 after the dieselization of MRR began. This is despite some seeing service as late as 1963 and a number of Porter locomotives were later used in movies as late as 1989. Two British-built are preserved in Manila and Dagupan as of 2020, and others were left rotting in rail yards.By 1956, MRR ordered 20 GE UM12C and 10 streamlined diesel locomotives intended to replace the pre-war Porter D class and US Army locomotives built during World War II. These were replaced by a large order of GE Universal Series locomotives in the 1960s and the 1970s and 10 of 75 units are still in service as of 2019, with 6 more units under refurbishment. By 2020, the PNR will receive three CC300 series diesel-hydraulic locomotives, its first order since 1973 and first reception since the last 900 class entered regular service in 1991. In addition, the PNR received two sets of switchers for depot work in Tutuban from Italian manufactuer SVI, the first European locomotives to serve the PNR system since the 1980s.
Class | Image | Manufacturer | Year Built | Units Built | Type | Max Speed | Status |
0-4-0 | Hunslet Engine Company | 1885 | 2 | Steam tank engine | Decommissioned | ||
2-6-2T | Kitson-Meyer | 1913 | 4 | Steam tank | Decommissioned | ||
A | Neilson and Company | 1886–88 | 14 | Steam tank | Decommissioned | ||
Murillo Type B | Dübs and Company | 1886–88 | 5 | Steam tank | Decommissioned, Unit 17 Urdaneta preserved in Dagupan | ||
NBL Type B | North British Locomotive Company | 1906–10 | 25 | Steam tank | Decommissioned | ||
D | Kerr, Stuart and Company H.K. Porter, Inc. | 1907, 1919–21 | 27 | Steam | Decommissioned | ||
E | North British Locomotive | 1909–14 | 8 | Steam tank | Decommissioned | ||
H | American Locomotive Company | 1912 | 5 | Steam | Decommissioned | ||
R | Maschinenfabrik Esslingen Swiss Locomotive and Machine Works | 1914 | 6 | Steam tank | Decommissioned | ||
V | Kerr, Stuart and Company | 1905 | 2 | Steam tank | Decommissioned 1963, Unit 778 preserved in Tutuban station | ||
W | Kerr Stuart | 1907 | 4 | Steam tank | Decommissioned in 1927 | ||
X | Kerr Stuart | 1907 | 8 | Steam tank engine | Decommissioned | ||
Y | Hunslet | 1886–88 | 3 | Steam tank engine | Decommissioned in 1927 | ||
100 | Vulcan Iron Works | 1948 | 7 | Steam | Decommissioned | ||
140 | Baldwin Locomotive Works | 1926–29 | 10 | Steam | Decommissioned | ||
200 | American Locomotive Company | 1922 | 10 | Steam | Decommissioned | ||
300 | Nippon Sharyo | 1951 | 10 | Steam | Decommissioned | ||
800 | Vulcan Iron Works | 1944–45 | 45 | Steam | Decommissioned by 1956. | ||
900 | GE Transportation | 1973–91 | 21 | Diesel-electric | In service | ||
1000 | GE Transportation | 1956 | 10 | Diesel-electric | Decommissioned | ||
1500 | Alsthom | 1966–1967 | 10 | Diesel-electric boxcab | Decommissioned in 1987 | ||
2000 | GE Transportation | 1956 | 20 | Diesel-electric Road switcher | Decommissioned in 1997 | ||
2500 | GE Transportation | 1965–79 | 43 | Diesel-electric switcher | 2 units in service | ||
3000 | GE Transportation | 1955 | 10 | Diesel switcher | Decommissioned | ||
3000 | GE Transportation | 1960 | 10 | Diesel-electric | Rebuilt and renumbered as "5000 Class" in 1992 | ||
5000 | GE Transportation | 1992 | 10 | Diesel-electric | Not in active service since 2017 | ||
8500 | GE Transportation | 1944 | 2 | Diesel-electric | Decommissioned | ||
CC203 | PT INKA GE Lokindo | 1998 | 1 | Diesel-electric | Operated with ICTSI Decommissioned, exported to Australia | ||
CC300 | PT INKA | 2020 | 3 | Diesel-hydraulic | Undergoing tests |
Coaches
PNR trains were traditionally consisted of locomotive-hauled coaches with some being refurbished from commuter rail to intercity use to accommodate the Bicol Express. However, since the early 2010s, the government has put several diesel multiple units into service which were either second-hand Japanese trainsets or the Hyundai Rotem EMU that was new at the time. Currently, the only locomotive-hauled railcar type in service are the 203 series-derived coaches which were EMUs stripped of motive power components which they have used during their Japanese service. By 2020, it is expected that a batch of 15 coaches will arrive from Indonesia.Class | Image | Manufacturer | Year Built | Units Built | Status |
7A-100 | Nippon Sharyo, Kinki Sharyo, Teikoku Sharyo, Mecano | 1949–1978 | — | Decommissioned before 1999. | |
CMC 200 | 1974 | — | 1 unit for its rerailment crew active as of 2019. | ||
7A-2000 | Niigata Engineering Fuji Heavy Industries Nippon Sharyo | 1969–1978 | 26 | Decommissioned | |
7A-2000 | Niigata Engineering Fuji Heavy Industries | 1972, 1974 | 5 | Decommissioned | |
NR-00 | Niigata Engineering Fuji Heavy Industries Nippon Sharyo | 1969–1978 | 10 | Decommissioned | |
14 series sleeper | Kawasaki Heavy Industries Fuji Heavy Industries Others | 1966–1979 | 10 | On storage | |
203 series-derived coaches | Kawasaki Heavy Industries Nippon Sharyo | 1982 | 29 | In service | |
INKA coaches | PT INKA | 2020 | 15 | Under construction |
Multiple units
The first multiple units in service with the PNR in 1948 were locally-constructed diesel multiple units fitted with Cummins engines, the first ones bulit by Filipinos. In 1955, the agency ordered another 20 diesel railcars from Japan. It was later complemented and replaced by the box-shaped CMC units built in 1973. The CMC units were used on the Mayon Limited and also became the first trains on the Peñafrancia Express service. The inter-city CMCs were replaced by new streamlined Peñafrancia Express trains in the 1980s while it continued to serve on the PNR Metro Commuter Line until 1999 when it was replaced by Japanese push-pull 7A class coaches.Since 2009, PNR has acquired several multiple units that were either given second-hand from Japan, or brand new from other countries. This began with the purchase of then brand-new Hyundai Rotem DMUs. This order was followed by several orders of mostly second-hand rolling stock from Japan. In 2018, PNR signed a deal with Indonesian rolling stock manufacturer Industri Kereta Api for purchase of another six sets of multiple units. By entering service in 2019, these were officially named the 8000 Class. The Department of Science and Technology also helped in building additional stock through the Hybrid Electric Train. This is the first trainset to be designed by Filipino engineers and the first locally-built multiple units since the 1948 Cummins railmotors. It was officially turned over to PNR on June 20, 2019. The government is currently negotiating with local companies for the HET's mass production.
In 2019, with the realization of the North–South Commuter Railway project that has been on hold, PNR ordered thirteen Sustina Commuter electric trains from Japan Transport Engineering Company and shall begin operations by 2021. The project will be the first part of the system-wide modernization of PNR from narrow gauge and diesel power to standard gauge and electric power that shall happen in the long term.
Class | Image | Type | Gauge | Manufacturer | Year Built | Top Speed | Units Built | Status |
Cummins Railmotor | DMU | MRR | 1948 | Decommissioned | ||||
Mitsubishi railcars | Diesel railcar | Mitsubishi Heavy Industries Tokyo Car Daichi Bussan | 1955 | 100 | Decommissioned in 1985 | |||
KiHa 52–100 | DMU | JNR | 1962–66 | 7 | In service | |||
KiHa 350 | DMU | Fuji Heavy Industries | 1961–66 | 6 | In service | |||
KiHa 59 | DMU | JNR | 1967–68 1989 | 3 | In service | |||
Mayon Limited DMU | DMU | JNR | 1973 | 16 | Decommissioned | |||
CMC 300 | DMU | JNR | 1974–76 | 60 | Decommissioned in 1999 | |||
Nikkō | DMU | JNR | 1974 1998 | 26 | 7 units refurbished in 1998 as Bicol Express T-577. Decommissioned in 2004. | |||
Hyundai Rotem DMU | DMU | Hyundai Rotem | 2009–10 | 18 | In service | |||
DOST HET | Hybrid DMU/BEMU | DOST–MIRDC Fil-Asia Automotive | 2019–20 | 5 | Prototype unit in service, more units in order | |||
8000/ 8100 | DMU | PT INKA | 2019–20 | 22 | In service | |||
Sustina/E233-type NSCR EMUs | EMU | J-TREC | 2021 | 104 | On order | |||
CRRC Intercity DMUs | DMU | CRRC Zhuzhou Locomotive | 2021 | 9 | On order |
Liveries
The Manila-Dagupan Railway, the Manila Railroad Company and the Philippine National Railways sported various liveries representing various eras of the company, usually to celebrate the arrival of new rolling stock. Each of these are painted by hand.Steam locomotive era (1892–1954)
There were no available colored images of Manila-Dagupan Railway and the Manila Railroad Company's rolling stock before the war so the color scheme of the carriages remains unknown. However, based on the surviving locomotives, the steam locomotives owned by the two companies sported a black-only livery like most of the notable American steam engines.Railmotor livery (1948)
The Cummins railmotors were colored black or white, and orange. The pre-war carriages salvaged and refurbished in the late 1940s also used this color scheme.MRR/PNR livery (1955)
The MRR celebrated the arrival of its first diesel rolling stock with its colors changed to dark green and yellow, or alternately to yellow-orange and dark green. The livery was retained when the Philippine government took over and renamed it the Philippine National Railways. During the transition to PNR, the old MRR monogram with a diamond-shaped seal was painted out and the PNR circular seal and monogram was placed on the front of the cab with yellow wing-like symbols outside it. The PNR acronym is also placed on the sides as well. By the 1980s, the diesel multiple units will have a yellow body and the wing-like symbols are colored dark green. A few locomotives sported a yellow-orange livery at that time.Commuter Motor Coach livery (c. 1978)
During the late 1970s, the Commuter Motor Coaches used on PNR's local train services in Metro Manila and the Bicol Region was colored white and navy blue.Metrotren livery (1990)
When President Corazon Aquino inaugurated the rebranded Manila commuter service as "Metrotren" in 1990, the CMC coaches were repainted to navy blue, white and red. This was also used for the 1998 restocking of the Bicol Express with the old Peñafrancia Express IC-888 train. This was used until the mid 2000s when both multiple unit types were changed to the navy blue livery.Philippines 2000 livery (1997)
The GE Universal Series-based 900, 2500 and 5000 classes sported a red livery celebrating Fidel Ramos' Philippines 2000 program. Although the PNR revised this livery after 2000, some retained it due to lack of maintenance funds and a 900 class survived with this livery in use until 2008. Some of the freight carriages had the Philippines 2000 name spray-painted on top the old green and yellow livery.Navy blue livery (c. 2000, 2011)
A navy blue livery was introduced after the expiry of the Philippines 2000 program. This followed after PNR acquired locomotive-hauled 12 and 14 series coaches from Japan. There are subtle differences with the coaches used on the Commuter Express and the Bicol Express. The Commuter Express trainsets were navy blue with orange highlights while the Bicol Express were navy blue with gold highlights. The PNR symbol on the Commuter Express was white while on the Bicol Express was gold. The locomotives' colors were also changed to navy blue and orange.This livery was re-introduced in 2011 although it was not used on the Bicol Express trainsets.
Filtrack livery (2009)
PNR attempted to revitalize the Bicol Express in 2009 with the support of president Gloria Macapagal Arroyo. This was supported with a change of logo and liveries. The coaches in PNR service used white and orange while the locomotives' cabs were colored white while the PNR monogram logo was sealed out. The trains also sported the "Filtrack" brand on the coaches and on the side of the locomotives. However, this was short lived after the Bicol Express stopped its services indefinitely. By 2015, all of the rolling stock followed the 2000s navy blue livery.INKA livery (2019)
The PNR announced another logo change and changes to its livery in 2019. This is after the Duterte administration under the Department of Transportation announced major reforms to the PNR. The PNR's monogram is now fully incorporated on a seal-type logo, bearing the agency's name and the year it was founded. The seal was also changed from orange and blue to golden yellow and navy blue. At the same time, the rolling stock also changed its liveries with regards to the arrival of the new rolling stock from Indonesia. The 203 series-based passenger cars' liveries did not change as of 2020.The first among the old rolling stock was the KiHa 350 and KiHa 59 series trains. After this was the Hyundai Rotem DMUs and finally, 900 series locomotive DEL 917 changed its livery to orange, similar to the upcoming CC300s. All multiple units were fitted with new windows to resist stoning. The colors however varied from one type of rolling stock to another but the common theme was the inclusion of orange, white, navy blue and black.