Connah's Quay Power Station


Connah's Quay Power Station is a 1,420 MW gas-fired power station to the west of Connah's Quay in Flintshire in north Wales. It is next to the A548, being tightly situated between the road and the south bank of the River Dee.

History

The current station is built on the site of a coal-fired power station. The old station was opened on the 16 September 1954 by Lord Citrine, the chairman of the British Electricity Authority. The station was originally planned to only be of 60 megawatts, but it was realised that a larger station would be needed. The coal-fired station was built in three stages, each stage having two 30 MW generating sets, giving a total generating capacity of 180 MW. The stages were completed in 1953, 1955 and 1957.
Coal was provided by train from the Point of Ayr undersea colliery. There were two unloading sidings controlled by Rockcliffe signalbox.
The electricity output and thermal efficiency of the station was as follows:
YearElectricity output, GWhThermal efficiency, %
195415.7125.69
1955228.2626.40
1956479.9127.00
1957750.7127.22
1958959.6827.59
19611066.81626.94
19621134.08926.92
1963882.68826.84
1972550.3824.97
1979498.0624.94
1982185.9424.70

The station was closed in 1984 and demolished in 1992.

Gas-fired CCGT station

Construction of the new gas-fired station began in July 1993. The station was built by GEC Alsthom and Henry Boot Construction, with design by Atlantic Projects. In 1999, Henry Boot Construction sued Alstom for breach of contract. The station was completed in March 1996 and cost £580m. It was officially opened by Margaret Beckett on 4 July 1997. In June 1998, the station's visitor centre opened. The station was initially owned by Powergen, who became E.ON UK in 2004 and was transferred to Uniper in 2015. The station is currently Uniper's largest CCGT power station.
The power station is not to be confused with the Deeside Power Station, a similar CCGT power station with two chimneys situated on the north bank of the River Dee, one mile to the east of the Connah's Quay station. The two plants are separated by the Flintshire Bridge, with many electricity pylons running alongside.

Specification

It is a CCGT type power station that runs on natural gas. It is made up of four 330 MW modules - hence the four chimneys. Each module has a General Electric Frame 9FA gas turbine, a Stein Industrie heat recovery steam generator and a steam turbine; in a single-shaft layout. The gas comes via an eighteen-mile pipeline from the Point of Ayr gas terminal, where gas is received from Eni's Celtic gas fields in Liverpool Bay via the Douglas Complex. The station opened soon after the gas from the field was first produced. The station employs around 81 people.

Gas treatment plant

The Point of Ayr terminal originally delivered per day at standard conditions of treated gas to Connah's Quay. The fuel gas requirement of power station was about ; this left a gas surplus of about per day. The quality of this gas, although adequate for use in the power station, was not suitable for delivery to the National Transmission System. Because of the high nitrogen content the Wobbe number was too low and the total sulphur content was too high. A gas treatment plant with a capacity of was constructed at Connah's Quay to treat the gas to a quality suitable for delivery to the NTS. The plant was owned and operated by PowerGen and started up in November 1997, the plant was built by Costain's, the capital cost of the project was £40 million.

Operation

In the gas treatment plant gas passes through molecular sieves to remove sulphur to less than 15 ppm and water to less than 1 ppm to prevent ice formation in the downstream refrigeration plant. The dry sulphur-free gas passes through an activated carbon bed to remove any mercury to protect the downstream aluminium heat exchangers. The gas then passes to the cryogenic nitrogen removal system where it is cooled to -100 °C by Joule–Thomson chilling. In the pre-separation column the gas is separated into a methane stream and a nitrogen-rich stream. In the low temperature double column the nitrogen-enriched gas is separated into the reject nitrogen stream containing less than 1.5% methane and a low pressure methane stream containing less than 1.5% nitrogen. The liquid methane stream is pumped to 10 bar and then to the sales gas compressors. The reject nitrogen stream is heated and used to regenerate the molecular sieves then the sulphur-rich gas is burnt in a thermal oxidiser. There are four electric motor-driven sales gas compressors each of capacity per day at standard conditions with a discharge pressure of 55-75 barg. Gas was exported through a 30-inch 3 km pipeline to Burton Point where it was delivered into the National Transmission System.
As the production of gas from the offshore field declined so there was no longer a surplus of gas available at Connah's Quay. The Burton Point terminal is now identified by National Grid as an NTS offtake supplying gas to Connah's Quay power station.