Project | Beginning | Inauguration | Function | Watercourse | Place |
Stormvloedkering Hollandse IJssel | 1954 | 1958 | Flood barrier | Hollandse IJssel | South Holland near Krimpen aan den IJssel |
Zandkreekdam | 1959 | 1960 | Dam | Zandkreek, Veerse Gat | Between Noord-Beveland and Zuid-Beveland on the east |
Veerse Gatdam | 1960 | 1961 | Dam | Veerse Gat | Between Noord-Beveland and Zuid-Beveland on the west |
Grevelingendam | 1958 | 1965 | Dam | Grevelingenmeer | Between Tholen and Schouwen-Duiveland |
Volkerakdam | 1957 | 1969 | Dam | Volkerak, Hollands Diep Meuse and Oosterschelde | Between South Holland and Zeeland |
Haringvlietdam | 1958 | 1971 | Dam and Flood barrier | Haringvliet | Between Voorne-Putten and Goeree-Overflakkee |
Brouwersdam | 1964 | 1971 | Dam | Grevelingenmeer | Between Goeree-Overflakkee and Schouwen-Duiveland |
Markiezaatskade | 1980 | 1983 | Dam | Scheldt–Rhine Canal, Markiezaatsmeer | Between Zuid-Beveland and Molenplaat |
Oosterscheldekering | 1960 | 1986 | Flood barrier | Oosterschelde | Between Schouwen-Duiveland and Noord-Beveland |
Oesterdam | 1979 | 1987 | Dam | Oosterschelde, Scheldt–Rhine Canal | Between Tholen and Zuid-Beveland |
Philipsdam | 1976 | 1987 | Dam | Oosterschelde | Between Grevelingendam and Sint Philipsland |
Bathse spuisluis | 1980 | 1987 | Lock | Volkerak, Markiezaatsmeer, Oosterschelde | Bath, Zeeland |
Maeslantkering | 1988 | 1997 | Flood barrier | Nieuwe Waterweg | Downstream Rotterdam South Holland |
Hartelkering | 1991 | 1997 | storm surge barrier | Hartelkanaal | Near Spijkenisse, South Holland |