Olympic-class ferry


The Olympic Class ferries are the newest vessels to the Washington State Ferries fleet. The ferries are intended to allow the agency to retire the aging Evergreen State-class ferries currently in service. The ferry design is based on the Issaquah-class ferries which have proven to be the most reliable and versatile in the fleet. The Olympic Class ferries are designed to serve all routes and terminals in the WSF system. All vessels were built in Washington as required by state law.

Ferries

Ferries in this class include:
In the early 2000s, WSF began planning a replacement for their aging Steel Electric-class ferries, which were built in 1927 and were WSF's oldest ferries. They were the only vessels in WSF's fleet that were able to run on the Port Townsend-Keystone route as no other vessel could be used in the small, shallow Keystone Harbor. WSF planned to move the ferry terminal out of Keystone Harbor and build a 144-car vessel to replace the 60-car Steel Electrics used on the route. Some local residents opposed this plan, so no new ferries were built. When the Steel Electrics were retired in 2007 due to hull corrosion, the WSF had no auto ferries able to serve the Port Townsend - Keystone route. WSF replaced the Steel Electrics with three smaller Kwa-di Tabil class ferries that carry 64 cars and entered service between November 2010 and January 2012.
It was announced on June 20, 2012 in The Seattle Times that State of Washington Transportation Secretary Paula Hammond had selected the name "Olympic Class" from more than 130 suggestions from department employees. On November 13, 2012 the Washington State Transportation commission named the first ferry and the second.
The Tokitaes hull was rolled out of the construction building onto a drydock on Saturday, March 2, 2013. It was joined by the superstructure from Nichols Brothers Boatbuilders of Freeland, Whidbey Island on Sunday, March 3, 2013. On Tuesday, March 5, 2013, the superstructure was on top of the hull.
The keel laying of the Samish happened on Friday, March 8, 2013. Washington State Governor Jay Inslee was the one to strike the first weld on the Samish.
Funding for a third Olympic class was authorized in the Spring 2014 session of the Washington State Legislature and the keel laying and first weld took place on December 9, 2014.
The name Chimacum was picked for the third ferry by the Washington State Transportation Commission in November 2014 after a public outreach process.
The Samish was accepted by Washington State Ferries on April 10, 2015 and officially christened on May 20 in Anacortes. The ship underwent two months of sea trials and crew training before entering service on the Anacortes/San Juan Islands route at the start of the Summer 2015 sailing season on June 14.
Funding for a fourth Olympic class was authorized in the 2015 session of the Washington State Legislature with construction beginning on January 4, 2016.
The Chimacum joined the fleet on 7 April 2017.
WSF took delivery of the Suquamish in July 2018, and the ship entered revenue service on the Mukilteo/Clinton run on October 4, 2018.
In 2019, the state legislature contracted with Vigor to build five additional Olympic-class vessels. The ferries in this second series will be powered by a hybrid diesel-electric powerplant built by ABB, with either on-board diesel engines or shore-based electrical connections charging a battery bank. The 2019 legislation allocated $99 million to the project, which funded design work, the purchase of major componants for two ferries, and the beginning of construction on the first vessel. As of mid-2020, Vigor planned to begin building the first hybrid Olympic-class ferry in 2021 for delivery in late 2023 or early 2024, contingent on the state allocating the remaining required funds in a 2021 session.